MASKELL STEPS UP TO MEET A TOUGHER DESIGN STANDARD

November 5, 2026
Picture this: Six enormous pressure vessels. A flammable working fluid. A international design standard for pressure vessels. Equipment that needed modifying. Resin supply disrupted by conflict in the Middle East. And three months to get the job done. Ouch.

Picture this: Six enormous pressure vessels. A flammable working fluid. A international design standard for pressure vessels. Equipment that needed modifying. Resin supply disrupted by conflict in the Middle East. And three months to get the job done. Ouch.

For most manufacturers, that's a decent list of reasons to say ‘No thanks’. Maskell Productions said ‘Yes’.

When Ormat needed six 110,000-litre glass-reinforced plastic(GRP) pressure vessels for Contact Energy’s 101 MW Te Mihi 2 geothermal project, it turned to a New Zealand company it already knew could solve difficult problems. What followed became one of the more technically demanding builds in Maskell’s history — and a useful example of what New Zealand’s composites sector can do when the pressure comes on.

The vessels store hot iso-pentane, a flammable, low-boiling-point fluid used in the plant’s binary-cycle process. Each tank had to withstand 2 bar pressure, with double-skin construction and Maskell’s Hydroguard™ system to detect leaks early. This was also Maskell’s first project requiring compliance with the ASME X pressure-vessel standard for tanks of thissize.

Not exactly an off-the-shelf order. But Maskell had a headstart: experience manufacturing more than 10,000 fuel storage tanks across Australasia, plus an established relationship with Ormat through the Te Huka geothermal project. The technical knowledge was there. The challenge was stretching it into new territory.

That meant developing a custom manufacturing method and retrofitting existing equipment to cope with bigger, heavier and more complex vessels. Meanwhile, disruption to international resin supplies added another headache. Through it all, an independent inspector checked manufacturing and quality at every stage.

From the first shell to inspection of the sixth and final vessel, the team completed the build in three months. The tanks successfully finished hydrostatic testing on site, with Maskell providing technical support. So the manufacturing milestone was achieved — with the final on-site verification still to follow.

There’s a bigger story here than six very large tanks. It’s about the confidence to take on a customer’s demanding brief, adapt the workshop, learn a new standard and deliver under scrutiny. That kind of capability matters as New Zealand builds its next generation of geothermal infrastructure.

And as for pressure? In this case, Maskell proved it could handle plenty of it — even before the vessels were filled.

 

www.maskell.co.nz

 